Photonews Logo Photonews logo
  • Home
  • Pakistan
    • Punjab
    • Sindh
    • Khyber Pakhtunkhwa
    • Azad Jammu Kashmir
    • Balochistan
    • Gilgit – Baltistan
  • World
  • Business
  • Entertainment
  • Videos
    Hunger Games Sunrise on the Reaping trailer
    EntertainmentVideos

    Hunger Games Prequel Trailer Sparks Fan Frenzy Over 10-Second Silent Cliffhanger

    November 21, 2025 3 Min Read
    Billie Eilish Elon Musk
    EntertainmentVideos

    Billie Eilish Criticizes Elon Musk, Calls Billionaire Wealth “Pathetic”

    November 14, 2025 3 Min Read
    Gen V Season 2 trailer
    Videos

    Gen V Season 2 Trailer Cast, Plot, Premiere Details

    July 26, 2025 3 Min Read
  • Sports
  • Technology
  • Offbeat
  • Blog
  • Contact
Reading: Karachi-Lahore Motorway: Irregularities alleged in award of Rs148bn motorway project
PhotoNews PakistanPhotoNews Pakistan
Font ResizerAa
Search
  • Home
  • Pakistan
    • Punjab
    • Sindh
    • Khyber Pakhtunkhwa
    • Balochistan
    • Azad Jammu Kashmir
    • Gilgit – Baltistan
  • World
  • Business
  • Entertainment
  • Videos
  • Sports
  • Technology
  • Offbeat
  • Blog
  • Contact
Have an existing account? Sign In
Follow US
© 2022 Photonews. All Rights Reserved.
PhotoNews Pakistan > Top News > Karachi-Lahore Motorway: Irregularities alleged in award of Rs148bn motorway project
Top News

Karachi-Lahore Motorway: Irregularities alleged in award of Rs148bn motorway project

Web Desk
By Web Desk Published December 12, 2015 6 Min Read
Share
SHARE

Islamabad: The National Highway Authority has awarded a contract of Rs148 billion to a Pakistan-China joint venture firm for building a 230-kilometre section of the Karachi-Lahore Motorway amid allegations of irregularities.

The project is a part of the China-Pakistan Economic Corridor (CPEC).

The NHA invited bids for the project in August and awarded it to the joint venture of China Railway 20 Bureau and ZKB of Pakistan at a cost of Rs148.654bn and issued a letter of intent (LoI) to the two firms on Dec 8.

It is believed that the NHA could have saved Rs24bn if the project, which is being funded through the Public Sector Development Programme (PSDP), would have been awarded according to “instruction of bidders” (IoB) or clauses of the contract.

One of the construction firms, which participated in the bidding process, has served a legal notice on the NHA for alleged irregularities.

The Frontier Works Organisation (FWO), another bidder, is said to be annoyed after its bid was rejected despite submitting what it claims the lowest bid of Rs134bn.

Some of the bidders have lodged complaints with the NHA that the successful bidder had allegedly reduced quantities and work material amounting to Rs10bn without reducing the cost of the project.

In the pre-bidding process, bidders were clearly told not to reduce quantities or the level of profile (thicknesses) of the road and also not to compromise on minimum material requirements. These instructions were given to ensure that bidders give a balanced bid which would guarantee completion of the project in accordance with desired specifications.

A senior FWO official expressed dissatisfaction over the rejection of the FWO’s bid and said: “There must be some unfair intentions behind the rejection of our bid.”

It has been observed that the NHA rejected the FWO’s bid of Rs134bn on the grounds that the firm had not completed any project above Rs91 billion and thus did not fulfil the criteria for entering the bidding process.

The NHA’s General Manager, Mukhtar Durrani, said that nothing wrong had been done in the award of the contract and any deviation from rules and clauses of the contract had already been agreed to by all stakeholders during pre-bidding meetings.

“If any bidder has any reservations, he should raise the issue before the NHA’s grievance redressal committee (GRC),” he said.

He said that one of the bidders had served a legal notice on the NHA, but added the authority had also given its reply to the notice.

Mr Durrani said the FWO bid was rejected because it was a unique engineering procurement and construction (EPC) project which had to be completed on a fast-track basis.

“We also had to keep in mind the financial status of the firms,” he said.

One of the alleged violations of contract rules was that the successful bidders had submitted separate bid securities with two different names, but not in the name of the JV even though Instructions to Bidders clause 15.1 of the bid documents said: “Each bidder shall furnish, as part of his bid, a bid security of an amount not less than Rs500 million in Pak rupees or an equivalent amount in any freely convertible currency. In case of a joint venture, bid security shall be submitted with name of proposed JV accordingly.”

The NHA GM said that the successful bidders had submitted separate bid securities instead of in the name of JV. “In fact bidders (local and foreign firms) had requested the NHA that they will make their JVs later but not at the time of submission of bid securities and, therefore, the NHA did not receive bid securities of successful bidders in the name of the JV,” he clarified.

A clause of the contract said: “Primarily, the bidders are not allowed to lower levels of profile and that bidders are advised to follow minimum specified design requirements at bidding stage”.

Another alleged anomaly in the award of the contact is that the successful bidders have submitted an undertaking that they will increase quantities during the progress of the project, but the NHA cannot entertain any such request and this facility has not been offered to any other bidder.

The NHA GM said that not only the firms in successful JV but all bidders have submitted such affidavits that in case of any shortcoming in their bids they will improve them after the bidding process is over.

Read : PM Nawaz in Karachi to inaugurate Khi-Lhr motorway project

Share This Article
Facebook Twitter Pinterest Whatsapp Whatsapp LinkedIn Email Copy Link Print
Leave a comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Advertisement

HBL Saving Made Easy
HBL Saving Made Easy

Recent Posts

gold price increase today

Gold Global Rate Hits $4,214, Local Tola at Rs443,762

Netflix bid for Warner Bros.

President Trump Questions Netflix’s $72 Billion Warner Bros.

travis kelce poor performance texans

Travis Kelce’s Rough Game Sparks Retirement Talk

Post Archives

More Popular from Photonews

24th Lux Style Awards 2025 Nominations
Entertainment

Lux Style Awards 2025 Nominations Announced, Ceremony in Karachi

12 Min Read
Pakistan Stock Exchange 2025
Business

KSE-100 Flat at 166,284 as PSX Sees Consolidation

2 Min Read
Imran Khan jail meetings banned
Pakistan

Govt Bans All Meetings with Imran Khan in Jail, Calls Him an “Extremist”

3 Min Read
Pakistan

Bilal Bin Saqib Resigns as Pakistan’s Crypto Minister

Bilal Bin Saqib, Pakistan's Minister of State for Crypto and Blockchain, has resigned from his post…

December 2, 2025
Pakistan

ECP Refuses to Recognize Gohar Ali Khan as PTI Chairperson

The Election Commission of Pakistan (ECP) has formally refused to recognise Barrister Gohar Ali Khan as…

December 7, 2025
Top NewsWorld

Joaquin Guzman Lopez, Son of ‘El Chapo’, Pleads Guilty to U.S. Drug Trafficking Charges

Joaquin Guzman Lopez, one of the four sons of imprisoned Mexican drug lord Joaquín "El Chapo"…

December 2, 2025
Sindh

Justice Zafar Ahmed Rajput Takes Oath as New Sindh High Court Chief Justice

Justice Zafar Ahmed Rajput formally assumed office as the new Chief Justice of the Sindh High Court (SHC) on…

December 6, 2025
PhotoNews Pakistan

Always Stay Up to Date

Subscribe to our newsletter to get our newest articles instantly!

Categories

  • World
  • Pakistan
  • Punjab
  • Sindh
  • Khyber Pakhtunkhwa
  • Balochistan
  • Azad Jammu Kashmir

 

  • Top News
  • Business
  • Entertainment
  • Sports
  • Videos
  • Tech
  • Offbeat
  • Blog

© 2024 Phototnews
All Rights Reserved.

Welcome Back!

Sign in to your account

Lost your password?